AJ Flight Reservations Pvt. Ltd. v. Commissioner of CGST, Delhi West & Anr.
Delhi High Court | W.P.(C) 6585/2024 | Refund – Delay in sanction | Judgment dated 08.05.2024
Relevant Provisions: Section 54 of the CGST Act, 2017
1. Facts of the Case (Paras 1–3)
The petitioner, AJ Flight Reservations Pvt. Ltd., invoked Article 226 seeking a mandamus for disbursal of refund amounting to ₹81,79,529/- along with statutory interest under Section 54 of the CGST Act. The refund application was filed on 31.01.2024. As recorded, the department did not issue any deficiency memo within the prescribed statutory timeline.
The petitioner asserted that more than 60 days had elapsed without communication from the proper officer. This prolonged administrative silence, according to the petitioner, violated the mandatory timelines envisaged in Section 54 and Rule 90 of the CGST Rules.
2. Questions / Issues (Implied by Paras 1–3)
-
Whether the department’s failure to issue a deficiency memo or process the refund within the statutory period of 60 days can justify a direction for expeditious disposal.
-
Whether the petitioner is entitled to a writ of mandamus directing refund processing in a time-bound manner.
-
Whether interest implications under Section 56 may arise due to delay attributable solely to departmental inaction.
3. Court’s Observations (Paras 3–4)
The Court noted that:
-
The refund claim had been filed on 31.01.2024.
-
As per the petitioner’s uncontested submissions, no deficiency memo had been issued to date.
-
Since the statutory period of 60 days had already elapsed, the proper officer was under a legal obligation to process the claim.
The Court held that such delay defeats the scheme of Section 54, which mandates timely processing of refund applications. The statutory discipline embedded in the Act cannot be frustrated by administrative inaction.
The Court therefore directed the proper officer to expedite and dispose of the refund application within two weeks in accordance with law.
4. Final Judgment / Verdict (Para 4)
The writ petition was disposed of with the direction that:
-
The proper officer shall process and dispose of the refund application within two weeks.
-
The petitioner shall be at liberty to seek further remedies if aggrieved by any order passed on the refund or on computation of interest.
The Court did not adjudicate on the merits of the refund but imposed a strict time-bound mandate to the authorities.
Classification of Case under GST Act, 2017
Category: Refund – Delay in sanction / non-issuance of deficiency memo
Relevant Provisions: Section 54 (Refund), Section 56 (Interest), Rule 90 (Deficiency Memo)
Cases Referred – Summary Table
No external cases were cited in the judgment.
Hence, the table records “Not applicable”.
| Case Name | Citation | Issue | Court’s Verdict |
|---|---|---|---|
| No case referred | — | — | — |
Between Fine Lines – Practical Takeaways for Trade
This judgment reinforces that refund processing timelines are mandatory and not optional. If the department neither issues a deficiency memo nor processes the refund within 60 days, taxpayers may directly approach the High Court for time-bound directions. The ruling encourages administrative accountability and signals that silence by the department cannot defeat statutory rights, including the right to interest for delays attributable to the authorities.
Disclaimer – “The above summary is for academic purpose only; not formal legal opinion. Seek professional opinion before application. Author or publisher or website shall not be responsible for any usage in any form.”

