Refund of GST on Pre-GST Contracts to be Decided in 90 Days by State

0
342

Case Title: M/s Bafna Construction v. State of Chhattisgarh & Ors.
Court Name: High Court of Chhattisgarh at Bilaspur
Petition Number: WPC No. 6014 of 2024
Category of Dispute: Refund
Date of Judgment: 04.12.2024
Relevant Sections: Article 226 of the Constitution of India; Circulars dated 28.01.2020 and 06.06.2018 (relating to refund of GST on old contracts)
CGST/IGST Act Sections: Section 54 (Refund of Tax), and transitional provisions under Section 142(10) CGST Act, 2017


Facts of the Case [Para 1–3]:

  1. The petitioner, M/s Bafna Construction, was awarded a contract at pre-GST rates.

  2. GST was levied during the execution phase post-implementation of GST.

  3. The Central Government had issued circulars clarifying that if contractors pay GST on such contracts, refunds may be granted upon submission of appropriate certification.

  4. The petitioner submitted such a claim for refund, citing applicable circulars (Annexure P/2 dated 28.01.2020 and 06.06.2018), but alleged that despite repeated follow-up, there was complete inaction by the State authorities.


Question(s) in Consideration [Para 1–3]:

  • Whether the State authorities are obligated to process and refund the GST amount collected from the petitioner in respect of a contract awarded at pre-GST rates.

  • Whether the inaction of State authorities violates the petitioner’s legal right under the circulars issued by the Central Government.


Observations of the Court [Para 3–4]:

  1. The Court noted that the State’s counsel did not oppose the petitioner’s contention but stated the claim would be verified and decided in accordance with the circulars.

  2. The Court emphasized that the State should consider the Central Government’s circulars and prior similar cases where refunds were issued.

  3. The Court observed that such refund issues must be addressed promptly and objectively, considering the documents and eligibility of the petitioner.


Judgment of the Court [Para 4–6]:

  • The Court directed the State authorities to process the refund application of the petitioner within 90 days from the date of receipt of the order.

  • It directed consideration of the circulars dated 28.01.2020 and 06.06.2018 and similar precedents of refund.

  • The writ petition was disposed of with the above directions for timely adjudication of the refund claim.


Between Fine Lines:

  • Contractors who paid GST on pre-GST contracts may claim refunds.

  • The State is bound to process such claims in light of Central Government circulars.

  • The Court mandated a decision within 90 days.

  • Inaction or delay in GST refunds on such matters can be challenged under Article 226.

  • Similar refund cases were cited as grounds for equitable relief.


Summary of Referred Cases:

Name of Case Citation Summary Verdict
Circular dated 06.06.2018 Not a judicial case Clarifies refund eligibility for GST paid on contracts awarded pre-GST Refund admissible subject to proof
Circular dated 28.01.2020 Not a judicial case Reinforces previous stand and procedural clarifications Refund to be processed upon certificate

Disclaimer – “The above summary is for academic purpose only; not formal legal opinion. Seek professional opinion before application. Author or publisher or website shall not be responsible for any usage in any form.”