Case Details:
Case Title: M/s Kapil Kumar Khattar v. Union of India & Ors.
Court: High Court of Jammu & Kashmir and Ladakh at Jammu
Petition Number: RP No.42/2024
Relevant Sections: Section 13, Section 14, and Clause 119 of Section 2 of CGST Act, 2017
Category of Dispute: Rate of GST / Works Contract / Contractual Terms
Date of Judgment: 08 April 2025
Relevant GST Notifications: SRO-GST-11 dated 08.07.2017, SRO-GST-2 (Rate) dated 22.08.2017, and SRO-GST-6 (Rate) dated 21.09.2017
Facts of the Case (¶1–¶5)
-
The petitioner submitted a bid for a works contract on 28.08.2017, relying on the GST Council’s recommendation (05.08.2017) to reduce GST from 18% to 12%, though the actual notification effecting this change was issued later on 21.09.2017. (¶3)
-
The bid was accepted, work commenced post notification, and subsequently, a letter demanding differential GST was issued by the Respondents on 16.06.2021. (¶3)
-
A similar issue raised by M/s Pardeep Electricals had already been decided earlier by this Court in WP(C) No.2183/2019, holding that recovery notices without a hearing violated natural justice but confirmed tax liability based on the rate applicable on bid date. (¶4)
-
The petitioner’s earlier writ (WP(C) No.1379/2021) was dismissed on 03.11.2023 in line with the judgment in WP(C) No.170/2021. The current petition seeks review of that decision. (¶4–5)
Question(s) in Consideration (¶5–¶6)
-
Whether the petitioner is liable to pay GST at 18% based on the rate applicable on the bid submission date, despite the later notification reducing the rate to 12%.
-
Whether Special Condition No.49 of the tender, which fixes GST rate as on the bid date, is contrary to Section 13 of CGST Act.
-
Whether the review petition raises any “error apparent on the face of record” or any “new fact” warranting reconsideration.
Observations of the Court (¶7–¶17)
-
No new facts or errors were found in the earlier judgment; review jurisdiction cannot be used to revisit concluded issues. (¶7)
-
Clause 49 of the contract clearly binds the contractor to GST rate as applicable on the bid’s last date and stipulates reimbursement/refund only in case of post-bid rate changes. (¶8–¶9)
-
Since the rate on 16.09.2017 (last date for bids) was 18%, the petitioner cannot claim 12% based on a future notification. (¶10)
-
GST Council’s recommendation does not equate to enforceable law; tax can be levied only via notification as per Article 265 of the Constitution. (¶10)
-
Argument based on SRO-GST-2 (Rate) dated 22.08.2017 was found to be inapplicable to the nature of petitioner’s works contract, which did not fall under specific government works listed therein. (¶13–¶16)
-
The petitioner neither challenged the validity of Clause 49 earlier nor showed that it violated any statutory provision. (¶11–¶12)
Judgment of the Court (¶18)
-
The Review Petition is dismissed, having found no merit or error in the earlier judgment dated 03.11.2023.
Between Fine Lines (Simplified Summary)
-
GST Council’s recommendation isn’t law until notified.
-
GST rate applicable on bid date (18%) binds the contractor.
-
Contract clause 49 legally ties parties to tax rates as on bid submission date.
-
Notification dated 21.09.2017 is not retrospectively applicable.
-
Review was rejected as it raised no new facts or legal grounds.
Summary of Referred Cases
| Name of Case | Citation | Summary | Verdict |
|---|---|---|---|
| M/s Pardeep Electricals & Builders Pvt Ltd | WP(C) No.2183/2019 | Held that demand without hearing violated natural justice; rate on bid date was binding. | Tax liability confirmed; notices quashed on procedural grounds |
| M/s Pardeep Electricals & Builders Pvt Ltd | WP(C) No.170/2021 | Reiterated that GST Council recommendation not enforceable until notified. | Writ dismissed |

