Case Title: M/s Sita Homes Pvt. Ltd. vs. State of Madhya Pradesh and Others
Court: High Court of Madhya Pradesh, Indore Bench
Petition Number: Writ Petition No. 34913 of 2024
Judgment Date: 20 November 2024
Category of Dispute: Rate of GST / Reimbursement of differential tax
Relevant Sections: Article 226 of the Constitution of India; Section 9, 15, and 31 of the CGST Act, 2017; Notification No. 24/2017-CT(R) dated 21.09.2017 and Notification No. 15/2021-CT(R) dated 18.11.2021
Facts (Paras 2–5)
The petitioner, M/s Sita Homes Pvt. Ltd., engaged in civil construction, executed contracts with a government entity (respondent no.2) for construction works at the 36th Battalion, SAF Kanki, Balaghat district, under agreements dated 07.01.2018 and 26.03.2018. The petitioner had been discharging GST on payments received under these contracts. Initially, as per Notification No. 24/2017-CT(R), GST on such works contracts for government entities was 12% (6% CGST + 6% SGST). Subsequently, Notification No. 15/2021-CT(R) increased the rate to 18% effective 01.01.2022.
Despite the rate change, the respondent continued to pay only 12% GST on running bills, compelling the petitioner to bear the remaining 6% differential from its own funds. The petitioner made representations seeking reimbursement, and by letter dated 26.09.2022, respondent no.2 acknowledged the liability but cited pending approval from the State Government, leading to this writ petition.
Questions before the Court (Para 1 & 6)
Whether the petitioner is entitled to reimbursement of the additional 6% GST for the period 01.01.2022 to 30.09.2022, and whether a writ petition is maintainable despite the arbitration clause in the contract when no factual dispute exists.
Observations (Paras 7–8)
The Court noted that no disputed question of fact existed, as both the petitioner and respondents accepted that the GST rate had been revised to 18% effective 01.01.2022. Since the liability was admitted, relegating the petitioner to arbitration would be unjustified. The State GST Department itself confirmed that the rate enhancement was statutory and binding upon the government entity making payments under the contract.
Judgment (Para 9–10)
The Court held that respondent no.2 (the government entity) is liable to pay the differential GST of 6% for the period from 01.01.2022 to 30.09.2022 within three months of receiving the certified order. Failure to comply would attract interest at 6% per annum from the date of entitlement. The writ petition was accordingly disposed of.
Table of Referred Cases
| Case Name | Citation / Court | Verdict / Principle |
|---|---|---|
| M/s Sita Homes Pvt. Ltd. v. State of M.P. | 2024:MPHC-IND:32863 | Government entity directed to reimburse 6% GST differential; writ held maintainable despite arbitration clause. |
Between Fine Lines
This ruling emphasizes that where GST rate revisions are statutorily mandated and undisputed, contractors working for government entities cannot be forced to absorb the differential tax burden. Even where contracts include arbitration clauses, writ jurisdiction under Article 226 remains open if the issue is purely legal and uncontested. It underscores the necessity for public sector undertakings to promptly align contract payments with statutory tax changes to avoid avoidable litigation and interest costs.
Disclaimer – “The above summary is for academic purpose only; not formal legal opinion. Seek professional opinion before application. Author or publisher or website shall not be responsible for any usage in any form.”

