Home Case Laws Refund of enhanced GST @18% directed as the public sector employer had...

Refund of enhanced GST @18% directed as the public sector employer had admitted liability for 6% differential amount but failed to release payment

0
176

Case Title: SKB Projects India Pvt. Ltd. v. State of Madhya Pradesh & Others
Court: High Court of Madhya Pradesh, Jabalpur Bench
Petition No.: Writ Petition No. 38356 of 2024
Date of Judgment: 15 January 2025
Category: Rate of GST / Refund of Differential Tax
Relevant Sections: Article 226 of the Constitution of India; Section 9 of the CGST/SGST Act, 2017; Notifications No. 24/2017–CT(R) dated 21.09.2017 and No. 15/2021–CT(R) dated 18.11.2021


Facts (Para 2–5 of the judgment)

The petitioner, SKB Projects India Pvt. Ltd., was engaged in construction and renovation of the Government New Law College, Indore, under Agreement No. 10/2021-22. The contract was executed with a government entity (respondent no. 2). Initially, GST was charged at 12% on construction services in terms of Notification No. 24/2017-CT(R). However, from 01.01.2022, by virtue of Notification No. 15/2021-CT(R), the applicable rate was enhanced to 18%.

Despite this statutory change, the respondent continued to make payments with GST at 12%, though the petitioner discharged GST at 18% and sought reimbursement for the 6% differential. Respondent no. 2 accepted liability in a letter dated 26.09.2022 but delayed payment citing absence of State Government approval.


Questions for Determination (Para 6–7)

Whether the petitioner was entitled to a writ of mandamus directing the State and its undertaking to release the admitted differential GST amount along with interest when liability was undisputed but payment withheld on administrative grounds.


Observations (Para 6–9)

The Court observed that there was no dispute of fact—rate enhancement under the GST law was statutorily mandated and acknowledged by the State entity itself. The contention regarding alternate remedy under the Arbitration Act was rejected as no factual inquiry was required.

The State GST Department had confirmed that from 01.01.2022, GST on such works was indeed 18%. Hence, withholding payment of the differential amount was unjustified. The earlier coordinate bench judgment dated 12.12.2024 (WP No. 39378/2024) on identical facts directed payment of 6% differential GST, forming a binding precedent.


Judgment (Para 9–10)

Applying the parity principle, the Court directed respondent no. 2 to pay the GST differential @6% for the period 01.01.2022 to 30.09.2022 within three months from receipt of the certified order, failing which interest @6% per annum would accrue from the date of entitlement. The petition was accordingly disposed of.


Summary of Referred Case

Case Name Petition No. Date Held Relevance
[Unnamed] (Division Bench of MP High Court) WP No. 39378 of 2024 12.12.2024 Directed payment of 6% differential GST from 01.01.2022 to 30.09.2022 to contractor working for a government entity Applied mutatis mutandis to SKB Projects case

Between Fine Lines

For contractors executing government works, GST rate increases are automatically binding on both payer and payee. Once the government entity acknowledges the rate change, withholding payment citing administrative approval lacks legal basis. Contractors can seek judicial enforcement without resorting to arbitration when facts are undisputed and liability is admitted.