Circular No.: 120/39/2019-GST
Date of Circular: 11th October 2019
Relevant Sections and Rules:
- CGST Act, 2017:
- Section 11(3): Power to insert explanations in exemption notifications
- Section 168(1): Power to issue instructions
- Notification Reference:
- Notification No. 11/2017-Central Tax (Rate) dated 28.06.2017
- Notification No. 17/2018-Central Tax (Rate) dated 26.07.2018, Sr. No. 3(vi)
Summary of Circular:
This circular clarifies the effective date of an explanation inserted via Notification No. 17/2018-CTR in the parent Notification No. 11/2017-CTR, specifically Sr. No. 3(vi) relating to construction services provided to Government and Local Authorities.
- Background of the Issue:
- Notification No. 17/2018-CTR dated 26.07.2018 inserted an explanation under Sr. No. 3(vi) of Notification No. 11/2017-CTR to clarify that:
“Activities or transactions undertaken by Government and Local Authority are excluded from the term ‘business’.”
- However, the notification also mentioned that it comes into effect from 27.07.2018, causing confusion about whether the explanation applied prospectively or retrospectively.
- Legal Provision – Section 11(3) of CGST Act:
- Section 11(3) empowers the Government to insert explanations in exemption notifications within one year of issuance.
- Such explanations take effect retrospectively as if they were part of the original notification.
- Clarification Issued:
- The explanation inserted vide Notification No. 17/2018-CTR was:
- Issued within the permitted one-year window, and
- Meant to clarify the original concessional entry from its date of inception: 21.09.2017.
- Therefore, the explanation is effective from 21.09.2017, not from 27.07.2018 as stated in the notification’s closing line.
Source: Circular No.: 120/39/2019-GST